I am using activiti work flow. i have done some flow and deployed. later i have change the flow and deployed again
now the old application getting issues after deploying new flow can u pleas help me
Hello,
Can you please mention here which type of issues you getting? or any error log?
Thanks
ContCentric
Hi,
If your new flow is a upgrade to old one by keeping the original tasks and flows intact, then you need to update the PROC_DEF_ID_ to new one in Activiti tables.