Hi everyone, I have a simple Activiti 5 bpm based on two lanes with id "group1" and "group2" and two user tasks "task1" and "task2", the first in lane "group1" and the other in lane "group2".
I would like to understand better the meaning of the lanes. Do they represent groups? I ask this because I expect that automatically at the start of the process, the activity "task1" is assigned to the users of "group1" without the need to value the "candidateGroups" field. But it doesn't happen.
Should I still value the "candidateGroups" variable in this case? If so, I don't understand the meaning of wool. Are they only used for a graphic scope?